Projects at a glance
Sector
Environmental Infrastructure
Discipline
Structural Steel Erection, HV Electrical & Mechanical, Piping Systems, Testing & Commissioning
Sector
Environmental Infrastructure
Discipline
Process Water Treatment Plant, Waste Water Treatment Plant and Seawater In-take, Deodorisation System
Sector
Environmental Infrastructure
Discipline
Process Water Treatment Plant, Waste Water Treatment Plant and Seawater In-take, Deodorisation System
Sector
Energy & Power
Discipline
Steel Fabrication, E&M
installation, Supply of
Components and PLC
System




Project
Retrofitted 3 x Flue Gas Desulphurization (FGD) Plants
Sector
Environmental Infrastructure
Discipline
Structural Steel Erection, HV Electrical & Mechanical, Piping Systems, Testing & Commissioning
Client
Hongkong Electric

Retrofitted 3 x large-scale Flue Gas Desulphurization (FGD) plants to the two existing 350MW coal-fired generating Units L4 & L5 and one existing 250MW coal-fired generating Unit L2 in Lamma power plants for reducing sulphur dioxide (SO2) emission which were in support of the Government’s policy objective to improve the air quality of the Pearl River Delta.
The contract was awarded to MYC Engineering, as the main contractor, which included the Scope of Works as follows :
  1. Steel fabrication, field erection of structural steelwork and flue gas ducts;
  2. E&M, piping systems and equipment installation works;
  3. Inspection, testing, commissioning, performance tests of these FGD plants and associated common facilities.
Adopted an innovative “top-down” construction method to build the steel absorber/scrubber of 12.5m in diameter and over 30m height in order to solve the extremely congested site constraint, which was among the most congested power plants in terms of space in the Asia Pacific.
In addition, it was well executed in heavy lifting with a combination of using a tower crane together with a deployment of a 500-tonne mobile hydraulic crane for lifting the major components (eg, over 22 tonne) of the Gas-Gas- Heater over 55 meters to the top of each absorber. This was carried out one-by-one over an operating power generation unit in Lamma Island.
Project
Hong Kong Sludge Treatment Facilities
Sector
Environmental Infrastructure
Discipline
Process Water Treatment Plant
Waste Water Treatment Plant and Seawater In-take
Deodorisation System
Client
Veolia, Leighton, John Holland JV

The Hong Kong Sludge Treatment Facility (HKSTF) is one of the world's largest sludge incineration facilities. HKSTF is equipped with the state-of-the-art thermal incineration technology to treat a maximum of 2,000 tonnes of wet sludge per day.

      

   Scope of Works
  1. Installation of Process Water Treatment Plant including the seawater desalination plant, which produces process water;
  2. Installation of Waste Water Treatment Plant. Wastewater is treated and reused to achieve zero effluent discharge into the sea; and
  3. Installation of Deodorization System which is used to ensure the air emission meets the highest environmental requirements and stringent emission standards.
Project
Major MHS Plant Refurbishment / Modernisation
Sector
Energy & Power
Discipline
Steel Fabrication, E&M installation, Supply of Components and PLC System
Client
Castle Peak Power Company

The contract was awarded to MYC Engineering, as the main contractor, which included the provision of project management, workforce, engineering personnel to undertake design, dismantling, fabrication, E&M installation, upgrade, supply of components and T&C activities.
  
Scope of Works
  1. Complete refurbishment of 41 coal handling conveyors incl. all line accessories such as vibrating screens, magnetic separators, junction houses, at Castle Peak Power Station;
  2. Electrical distributions, transfer chutes, transfer towers, and dust suppressions and vacuum systems; and
  3. Plant controls, automation of bunkering system, pull wire switch monitoring system, etc.
ENG
項目概覽
建造3台煙氣脫硫(FGD)設備於現有發電機組

行業範疇
環境基礎設施
專業介別
鋼結構,機電設備,管道系統安裝工程,煙氣脫硫裝置性能測試
香港污泥處理設施 [源 · 區]

行業範疇
環境基礎設施
專業介別
過瀘水處理廠
污水處理廠及海水入口,除臭系統
物料輸送系統設備翻新 / 現代化工程

行業範疇
能源與動力
專業介別
鋼結構製造,機電安裝,電源組件供應和PLC系統設計
項目名稱 建造3台煙氣脫硫(FGD)設備於現有發電機組
行業範疇 環境基礎設施
專業介別 鋼結構,機電設備,管道系統安裝工程,煙氣脫硫裝置性能測試
客戶 香港電燈

該項目合同由華昌工程承辦並為主承辨商。在南丫島發電廠內建造3台大型煙氣脫硫(FGD)設備接駁至現行兩組350MW編號L4及L5燃 煤發電機和一組250MW 編號L2燃煤發電機。此項目主要用以減少現有二氧化硫(SO2)的排放量並為配合政府排放政策的目標,以改善珠江三角地區的空氣質量。

合同工作範圍包括

  1. 鋼結構及煙氣管道製造和安裝;
  2. 機電設備及管道系統安裝;
  3. 檢驗,檢測及調試煙氣脫硫裝置的性能和其他相關的公用設備。

此項目採用創新的“自上而下”的施工方法,建造12.5米直徑及超過30米高度的鋼製吸收器/滌氣器。此方法專為解決在亞太地區電廠內擠廹空間的環境限制而設。

此外,組合使用塔式起重機與500噸的移動式液壓起重機以安裝燃氣發熱器(GAS-GAS-HEATER)的主要部分(超過22噸)上升超過55米高 度至吸收器的頂部。此部份在發電電機組運行中逐一進行。

項目名稱 香港污泥處理設施 [源 · 區]
行業範疇 環境基礎設施
專業介別 過瀘水處理廠
污水處理廠及海水入口,除臭系統
客戶 威立雅,禮頓,賀倫聯營公司
香港污泥處理設施(HKSTF)是世界上最大的污泥焚燒設備之一。HKSTF配備外國最先進的熱焚燒技術,每天能處理最高2,000噸的濕污泥。

工作範圍
  1. 安裝濾水處理廠,包括海水淡化廠,生產過瀘水。
  2. 安裝污水處理廠。廢水處理和循環再用,實現污水零排放入海。
  3. 安裝脫臭系統,用以確保氣體排放符合最高環保要求和嚴格的排放標準。
項目名稱 物料輸送系統設備翻新 / 現代 化工程
行業範疇 能源與動力
專業介別 鋼結構製造,機電安裝,電源組件供應和PLC系統設計
客戶 中華電力青山發電厰
該合同由華昌工程承辦。作為主承辦商,工作範圍包括提供:項目管理,人力資源,工程設計,舊裝備拆卸,新機電組件安裝,升級,電源組件供應,測試及調試等。

工作範圍
  1. 在青山發電廠內修建41項運煤輸送帶,包括所有煤帶的配件,例如振動篩,磁選機,接駁系統等;
  2. 電氣配電,轉讓槽,傳輸塔,和灰塵壓抑器和真空系統;
  3. 系統控制,自動化供料系統,拉線開關監控系統等。